Question: The following table provides data for a project. Use the data to answer the following questions Activity Immediate Predecessor Time Estimates (weeks) Optimistic Most Likely

The following table provides data for a project. Use the data to answer the following questions

Activity

Immediate

Predecessor

Time Estimates (weeks)

Optimistic

Most Likely

Pessimistic

Expected

Variance

A

-

6

7

14

8

1.78

B

-

8

10

12

10

.44

C

A

2

3

4

3

.11

D

A

6

7

8

7

.11

E

B,C

5

5.5

9

6

.44

F

B,C

5

7

9

7

.44

G

D,E

4

6

8

6

.44

H

F

2.5

3

3.5

3

.0278 = .03

  1. Draw a network to represent the above project.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!