Question: The following table provides data for a project. Use the data to answer the following questions Activity Immediate Predecessor Time Estimates (weeks) Optimistic Most Likely
The following table provides data for a project. Use the data to answer the following questions
| Activity | Immediate Predecessor | Time Estimates (weeks) | ||||
| Optimistic | Most Likely | Pessimistic | Expected | Variance | ||
| A | - | 6 | 7 | 14 | 8 | 1.78 |
| B | - | 8 | 10 | 12 | 10 | .44 |
| C | A | 2 | 3 | 4 | 3 | .11 |
| D | A | 6 | 7 | 8 | 7 | .11 |
| E | B,C | 5 | 5.5 | 9 | 6 | .44 |
| F | B,C | 5 | 7 | 9 | 7 | .44 |
| G | D,E | 4 | 6 | 8 | 6 | .44 |
| H | F | 2.5 | 3 | 3.5 | 3 | .0278 = .03 |
- Draw a network to represent the above project.