Question: The following table represents a plan for a project: m JOB NO. 1 2 3 4 5 6 7 8 9 10 11 PREDECESSOR TIMES

The following table represents a plan for a
The following table represents a plan for a
The following table represents a plan for a project: m JOB NO. 1 2 3 4 5 6 7 8 9 10 11 PREDECESSOR TIMES (DAYS) JOB(S) a b 2 4 9 1 2 2 11 1 2 4 6 1 3 7 8 2 2 3 4 3 1 2 6 4 3 5 10 5,6 1 3 5 8 1 2 12 7 3 4 5 9,10 1 5 6 Yos e. What is the probability that the project will take more than 29 days to complete? (Round your answer to 2 decimal places.) Probability