Question: The following table represents a plan for a project: PREDECESSOR JOB(S) TIMES (DAYS) JOB NO. a m b 1 2 3 4 2 1 1
The following table represents a plan for a project:
| PREDECESSOR JOB(S) | TIMES (DAYS) | |||
| JOB NO. | a | m | b | |
| 1 | 2 | 3 | 4 | |
| 2 | 1 | 1 | 7 | 13 |
| 3 | 1 | 4 | 5 | 12 |
| 4 | 1 | 3 | 3 | 9 |
| 5 | 2 | 3 | 4 | 5 |
| 6 | 3 | 1 | 2 | 3 |
| 7 | 4 | 2 | 9 | 10 |
| 8 | 5,6 | 1 | 3 | 5 |
| 9 | 8 | 2 | 4 | 12 |
| 10 | 7 | 3 | 4 | 5 |
| 11 | 9,10 | 3 | 10 | 11 |
b. Indicate the critical path.
-
1-3-6-8-9-11
-
1-2-5-8
-
1-4-7-10-11
-
1-2-5-8-9-11
c. What is the expected completion time for the project? (Round your answer to 2 decimal places.)
Expected completion time days
d. You can accomplish any one of the following at an additional cost of $1,500 and if you will save $1,000 for each day that the earliest completion time is reduced, which action, if any, would you choose?
1. Reduce job 3 by three days.
-
Yes
-
No
2. Reduce job 7 by two days.
-
Yes
-
No
3. Reduce job 8 by four days.
-
No
-
Yes
e. What is the probability that the project will take more than 33 days to complete? (Round your answer to 2 decimal places.)
Probability
Step by Step Solution
There are 3 Steps involved in it