Question: The following table represents a plan for a project: PREDECESSOR JOB(S) TIMES (DAYS) JOB NO. a m b 1 2 3 4 2 1 1

The following table represents a plan for a project:

PREDECESSOR JOB(S) TIMES (DAYS)
JOB NO. a m b
1 2 3 4
2 1 1 7 13
3 1 4 5 12
4 1 3 3 9
5 2 3 4 5
6 3 1 2 3
7 4 2 9 10
8 5,6 1 3 5
9 8 2 4 12
10 7 3 4 5
11 9,10 3 10 11

b. Indicate the critical path.

  • 1-3-6-8-9-11

  • 1-2-5-8

  • 1-4-7-10-11

  • 1-2-5-8-9-11

c. What is the expected completion time for the project? (Round your answer to 2 decimal places.)

Expected completion time days

d. You can accomplish any one of the following at an additional cost of $1,500 and if you will save $1,000 for each day that the earliest completion time is reduced, which action, if any, would you choose?

1. Reduce job 3 by three days.

  • Yes

  • No

2. Reduce job 7 by two days.

  • Yes

  • No

3. Reduce job 8 by four days.

  • No

  • Yes

e. What is the probability that the project will take more than 33 days to complete? (Round your answer to 2 decimal places.)

Probability

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock