Question: The following table represents a plan for a project: TIMES (DAYS) JOB NO. PREDECESSOR JOB(S) a m b 1 1 3 8 2 1 3
| The following table represents a plan for a project: |
| TIMES (DAYS) | ||||
| JOB NO. | PREDECESSOR JOB(S) | a | m | b |
| 1 | 1 | 3 | 8 | |
| 2 | 1 | 3 | 3 | 6 |
| 3 | 1 | 3 | 6 | 12 |
| 4 | 1 | 5 | 7 | 12 |
| 5 | 2 | 3 | 6 | 12 |
| 6 | 3 | 1 | 2 | 3 |
| 7 | 4 | 2 | 9 | 10 |
| 8 | 5, 6 | 2 | 4 | 6 |
| 9 | 8 | 2 | 4 | 12 |
| 10 | 7 | 4 | 4 | 7 |
| 11 | 9, 10 | 2 | 11 | 11 |
|
| ||||
| b. | Indicate the critical path. |
Options:
|
| c. | What is the expected completion time for the project? (Do not round intermediate calculations. Round your answer to 2 decimal places.) |