The following table represents a plan for a project:

TIMES (DAYS)

JOB NO. PREDECESSOR JOB(S) a m b
1 1 3 8
2 1 3 3 6
3 1 3 6 12
4 1 5 7 12
5 2 3 6 12
6 3 1 2 3
7 4 2 9 10
8 5, 6 2 4 6
9 8 2 4 12
10 7 4 4 7
11 9, 10 2 11 11

b. Indicate the critical path.
Options:
  • 1-2-5-8-9-11

  • 1-4-7-10-11

  • 1-2-5-8

  • 1-3-6-8-9-11

c.

What is the expected completion time for the project? (Do not round intermediate calculations. Round your answer to 2 decimal places.)