Question: The following table represents a project with four activities. All times are in weeks. Using the data in the table, what is the critical path?
The following table represents a project with four activities. All times are in weeks.
Using the data in the table, what is the critical path?
Question options:
ABCD
AC
BD
AB
None of the above