Question: The following table shows normal time, normal cost, crash time, and crash cost of a project. We are trying to crash this project by one

The following table shows normal time, normal cost, crash time, and crash cost of a project. We are trying to crash this project by one day. If the critical path is A-D-F-G, which activity should we c 