Question: The following table shows normal time, normal cost, crash time, and crash cost of a project. Normal Crash Activity ID Maximum Time (day) Cost crash

The following table shows normal time, normal cost, crash time, and crash cost of a project. Normal Crash Activity ID Maximum Time (day) Cost crash time Time (day) Cost A 3 $50 2 $75 B 2 6 80 4 160. C 1 10 60 9 90 D 4 11 50 7 130 E 8 100 6 160 1 5 40 4 70 G 0 6 70 6 70 We are trying to crash this project by one day. If the critical path is A-D-F-G, which activity should we crash? (.1 pt) Show all your cost slope calculations (.2 pt) and explain how you decided which activity to crash (.2 pt)