Question: The forward pass algorithm is used to Question 1 3 options: Determine the critical path Estimate activity duration Evaluate project risk Transition the project to
The forward pass algorithm is used to
Question options:
Determine the critical path
Estimate activity duration
Evaluate project risk
Transition the project to the project sponsor