Question: The free float and total float for activity a in a project for 5 days and 8 Days respectively the early start date of activity

The free float and total float for activity a in a project for 5 days and 8 Days respectively the early start date of activity a is delayed by 7 days, which corrective action would you take to ensure that the project fish is on the plan date number one you use fast tracking for some of the activities number two, you would crash some of the subsequent activities number three, you would not do anything number four. You would call a meeting of the stakeholders.