Question: In your project, you have two activities, D and E. These two activities have a common successor, Activity F. Activity D will be completed on
In your project, you have two activities, D and E. These two activities have a common successor, Activity F. Activity D will be completed on the 10th and activity E will be completed on the 15th. Therefore, Activity D can be delayed by 5 days without affecting the early start of Activity F. This delay is known as:
(a) Total float
(b) Free float
(c) Project buffers
(d) Feeding buffer