Question: The Fresh Connection is looking at the needs for a new processing operation. The demand at this operation is 259 units per day. Given the

The Fresh Connection is looking at the needs for a new processing operation. The demand at this operation is 259 units per day. Given the combination of regular time, overtime and some additional time available due to cross training, this operation is up and running for 20.7 hours per day across multiple shifts.

Task Time Req. (min.) Predecessor Tasks
a 7.24 -
b 20.78 a
c 7.36 b
d 6.46 c
e 11.03 d
f 10.43 e
g 22.62 f
h 7.05 g

Assume that each task must be completed in sequence but that you can combine some tasks so that the tasks can be completed on a total of six workstations without increasing the cycle time beyond what it would be if each task had its own workstation. How much more efficient is the process compared to using eight workstations (stated as the difference between the two percents)?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!