Question: The immediate --------- must be completed before the next activity can start in the project network a) Critical activities b) Burst activities c) Predecessor activities
The immediate --------- must be completed before the next activity can start in the project network a) Critical activities b) Burst activities c) Predecessor activities d) Successor activities e) None of the above f) All of the above