Question: The information about a project with 10 activities is shown below. Activity A; 25 days; IP = none Activity B; 21 days; IP = none

The information about a project with 10
The information about a project with 10 activities is shown below. Activity A; 25 days; IP = none Activity B; 21 days; IP = none Activity C; 7 days; IP = A Activity D; 17 days; IP = A, B Activity E; 10 days; IP = B Activity F; 13 days; IP = C Activity G; 33 days; IP =D Activity H; 16 days; IP = E Activity K; 20 days; IP = F, G Activity M; 20 days; IP = G, H The slack of activity Fis days