Question: The information about a project with 10 activities is shown below. Activity A; 18 days; IP = none Activity B; 10 days, IP = none

The information about a project with 10
The information about a project with 10 activities is shown below. Activity A; 18 days; IP = none Activity B; 10 days, IP = none Activity C; 8 days, IP = A Activity D, 21 days, IP = A, B Activity E, 25 days, IP=B Activity F; 13 days, IP = C Activity G, 27 days, IP =D Activity H; 31 days; IP = E Activity K, 11 days, IP = F, G Activity M; 15 days; IP = G, HI The earliest start time of activity K is at the end of day