Question: The information about a project with 10 activities is shown below. Activity A; 8 days; IP = none Activity B; 11 days; IP = none

The information about a project with 10
The information about a project with 10 activities is shown below. Activity A; 8 days; IP = none Activity B; 11 days; IP = none Activity C; 12 days; IP = A Activity D; 16 days; IP = A, B Activity E; 18 days; IP = B Activity F: 23 days; IP = C Activity G: 31 days; IP =D Activity H: 28 days; IP = E Activity K; 7 days; IP = F, G Activity M; 19 days: IP = GH The earliest start time of activity K is at the end of day