Question: The interactive, collaborative scheduling technique where the team works backwards from a completion milestone and defines the key lead - in work to achieve the

The interactive, collaborative scheduling technique where the team works backwards from a
completion milestone and defines the key lead-in work to achieve the event is called?
Lean Construction
Pull Planning
AWP (Advance Work Packaging)
Public-Private Partnership
CPM Scheduling
 The interactive, collaborative scheduling technique where the team works backwards from