Question: The inventory on hand, and the product structure tree, for a certain product are given below. LT refers to lead time in weeks and the
The inventory on hand, and the product structure tree, for a certain product are given below. LT refers to lead time in weeks and the number in brackets ( ) refers to the number of units required.

| Component | A | B | C | D | E | F |
| Inventory on Hand | 15 | 10 | 25 | 30 | 10 | 15 |
1. If an order for A is scheduled to be shipped at the start of week 12, what is the latest week that the order can be started and still be ready to ship on time.
| 4 | ||
| None of the other options are correct | ||
| 5 | ||
| 8 | ||
| 6 |
2. How many units of C are required to make one A
| 8 | ||
| 4 | ||
| 5 | ||
| 6 | ||
| None of the other options are correct |
3. How many units of E are required to make one A
| None of the other options are correct | ||
| 5 | ||
| 9 | ||
| 6 | ||
| 3 |
4. If 60 units of A are required, how many additional units of C should be ordered
| None of the other options are correct | ||
| 215 | ||
| 200 | ||
| 255 | ||
| 150 |
5. If 60 units of A are required, how many additional units of E should be ordered?
| 140 | ||
| None of the other options are correct | ||
| 150 | ||
| 130 | ||
| 180 |
Step by Step Solution