Question: The inventory on hand, and the product structure tree, for a certain product are given below. LT refers to lead time in weeks and the

The inventory on hand, and the product structure tree, for a certain product are given below. LT refers to lead time in weeks and the number in brackets ( ) refers to the number of units required.

Component

A

B

C

D

E

F

Inventory on Hand

15

10

25

30

10

15

1. If an order for A is scheduled to be shipped at the start of week 12, what is the latest week that the order can be started and still be ready to ship on time.

4

None of the other options are correct

5

8

6

2. How many units of C are required to make one A

8

4

5

6

None of the other options are correct

3. How many units of E are required to make one A

None of the other options are correct

5

9

6

3

4. If 60 units of A are required, how many additional units of C should be ordered

None of the other options are correct

215

200

255

150

5. If 60 units of A are required, how many additional units of E should be ordered?

140

None of the other options are correct

150

130

180

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!