Question: The letters in the table below represent work elements in an assembly precedence diagram work element A B C D E F G H I
- The letters in the table below represent work elements in an assembly precedence diagram
| work element | A | B | C | D | E | F | G | H | I | J | K | L | M | N |
| Time (min) | 0.5 | 0.3 | 0.8 | 1.1 | 0.6 | 0.2 | 0.7 | 1.1 | 0.9 | 0.4 | 0.7 | 0.1 | 1.3 | 1.1 |
| Preceding | - | - | A | B | C | B,C | D | E,G | F | H,I | J | J | K, L | M |
(a) Construct the precedence diagram and determine the total work content time.
(b) Use the Kilbridge & Wester Method method to assign work elements to stations using a service time (Ts) of 1.8 min. How many workstations are needed?
(c) compute the balance delay for your solution.
(d) If M=2 how many workers company need for the system. (based on the number of workstations that are founded)
Step by Step Solution
There are 3 Steps involved in it
The question is complete Lets proceed step by step a Construct the Precedence Diagram and Determine the Total Work Content Time Step 1 Identify Preced... View full answer
Get step-by-step solutions from verified subject matter experts