Question: The local university has developed an eight-step process for screening the thousands of admissions applications it gets each year. The provost has decided that the

The local university has developed an eight-step process for screening the thousands of admissions applications it gets each year. The provost has decided that the best way to take a first cut at all these applications is by employing a line process. The following table shows the times and predecessors for the various tasks:

Task

Time (minutes)

Immediate predecessor

A

1.2

None

B

1

A

C

0.85

B

D

1.1

B

E

1.3

C

F

0.7

D

G

0.8

D

H

0.9

E, F, G

3.) How many workstations does your solution require? What is the cycle time? What is the idle time? What are percent idle time and the efficiency?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!