Question: The lowest levels to include in a work breakdown structure Question 1 6 Answer a . have each task completed by one person. b .
The lowest levels to include in a work breakdown structure
Question Answer
a
have each task completed by one person.
b
are at a level which the project manager wants to monitor and control the project performance.
c
have each task completed in one day.
d
should be the same for all the divisions.