Question: The lowest levels to include in a work breakdown structure Group of answer choices should be the same for all the divisions. are at a

The lowest levels to include in a work breakdown structure Group of answer choices should be the same for all the divisions. are at a level which the project manager wants to monitor and control the project performance. have each task completed in one day. have each task completed by one person