Question: The method of calculating the EAC by adding the remaining project budget ( modified by the performance factor ) to the actuals to date is

The method of calculating the EAC by adding the remaining project budget (modified by the performance factor) to the actuals to date is used most often when the
a. Current variances are atypical ones
b. Original estimating assumptions are no longer reliable due to project changes
c. Current variances are viewed as typical of future variances
d. Original estimating assumptions are considered to be fundamentally flawed
Select one of the above options