Question: . A project manager practices cost control for his projects by calculating an EAC. Calculating the EAC by adding the remaining project budget (modified by
. A project manager practices cost control for his projects by calculating an EAC. Calculating the EAC by adding the remaining project budget (modified by a performance factor) to the actual cost to date is used most often when the:
a) Current variances are viewed as atypical ones
b) Original estimating assumptions are no longer reliable because conditions are changing
c) Current variances are viewed as typical of future variances
d) Original estimating assumptions are considered to be fundamentally flawed