Question: The MOQ for the washer is 24 and the batch quantities for are in 12s. the end products have to leave the manufacturing organisation in
The MOQ for the washer is 24 and the batch quantities for are in 12s.
the end products have to leave the manufacturing organisation in 12 weeks. the production time to make the washers into the end product is four weeks. the lead time on thw washers is six weeks.
what is the minimu amount of the washers that need to be ordered to meet all the needs?
if today is the start of week one, what week does the buyer have to place the order to ensure that the end product is made in time