Question: The most common method for shortening activity durations involves the decision to: Question 9 Select one: a . Increase project resources. b . Alter the

The most common method for shortening activity durations involves the decision to:
Question 9Select one:
a.
Increase project resources.
b.
Alter the technology used in the activity.
c.
Assign more senior personnel to the activity.
d.
Eliminate bureaucracy.