Question: The most common method for shortening activity durations involves the decision to: Question 9 Select one: a . Increase project resources. b . Alter the
The most common method for shortening activity durations involves the decision to:
Question Select one:
a
Increase project resources.
b
Alter the technology used in the activity.
c
Assign more senior personnel to the activity.
d
Eliminate bureaucracy.