Question: The MPS start quantities for product A calls for the assembly department to begin final assembly according to the following schedule: 100 units in week

The MPS start quantities for product A calls for the assembly department to begin final assembly according to the following schedule: 100 units in week 2; 200 units in week 4; 120 units in week 6; 180 units in week 7; and 60 units in week 8.

Develop a material requirements plan with these theqnique EOQ, POQ and L 4 lot.

(Ordering cost and holding cost values are not given with the question.)

0 1 2 3 4 5 6 7 8 9 10
Gross Requirement 100 200 120 180 60
Schedule Reciept
Project onhand 20
Planned Reciept
Planned order Release

Please explain step by step how you solve it.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!