Question: The MPS start quantities for product A calls for the assembly department to begin final assembly according to the following schedule: 120 units in week

The MPS start quantities for product A calls for
The MPS start quantities for product A calls for
The MPS start quantities for product A calls for the assembly department to begin final assembly according to the following schedule: 120 units in week 2; 250 units in week 4 140 units in week 6; 140 units in week 7 50 units in week 8. Develop a material requirements plan for the next 8 weeks for items B, C, and D