Question: The network below represents a project being analyzed by Critical Path Methods. Activity durations are A=5, B=2, C=12, D=3, E=5, F=1, G=7, H=2, I=10, and

The network below represents a project being analyzed by Critical Path Methods. Activity durations are A=5, B=2, C=12, D=3, E=5, F=1, G=7, H=2, I=10, and J=6.

Activity Time (weeks)

Activity Cost ($)

Activity

Activity Predecessor

Normal

Crash

Normal

Crash

A

--

16

8

2000

4400

B

--

14

9

1000

1800

C

A

8

6

500

700

D

A

5

4

600

1300

E

B

4

2

1500

3000

F

B

6

4

800

1600

G

C

10

7

3000

4500

H

D, E

15

10

5000

8000

The network below represents a project beingThe network below represents a project being

Question: Use the constructed project network, and crash the network the maximum amount possible

Results Task A B C D E F G H I J Early Start 0 5 5 0 7 3 7 17 14 24 Project Early Finish 5 7 17 3 12 4 14 19 24 30 30 Late Start 0 5 10 10 17 13 7 22 14 24 Late Finish 5 7 22 13 22 14 14 24 24 30 Slack 0 0 5 10 10 10 0 5 0 E B H A Start 12 D 1 F 10

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!