Question: The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network. a. saentiry tne activities on

 The network below represents a project being analyzed by the critical

The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network. a. saentiry tne activities on me crincal patr. b. What is the duration of the critical path? c. Calculate the amount of slack time at activity H. d. If activity I were delayed by ten time units, what would be the impact on the project duration