Question: The network below represents a project being analyzed by the critical path method Activity durations are A=5,B=2,C=12,D=3,E=5,F=1,G=7,H=2,I=10 , and J=6 . a. What task must
The network below represents a project being analyzed by the critical path method Activity durations are A=5,B=2,C=12,D=3,E=5,F=1,G=7,H=2,I=10 , and J=6 . a. What task must be on the critical path, re