Question: The network below represents a project being analyzed by the critical path method. Activity durations are A = 5, B = 2, C = 12,

The network below represents a project being analyzed by the critical path method. Activity

durations are A = 5, B = 2, C = 12, D = 3, E = 5, F = 1, G = 7, H = 2, I = 10, and J = 6.

What is the duration of the path A-B-E-H-J

a.

25

b.

30

c.

20

d.

21