Question: The network below represents a project being analyzed by the critical path method. Activity durations are A = 5, B = 2, C = 12,

The network below represents a project being

The network below represents a project being analyzed by the critical path method. Activity durations are A = 5, B = 2, C = 12, D = 3, E = 5, F = 1, G = 7, H = 2, 1 = 10, and J = 6. E H A Start 10 What is the duration of the path A-B-E-H-J a. 21 O b. 25 O c. 30 O d. 20