Question: The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network. End E Start a) Find

The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network. End E Start a) Find the earliest as well as latest start and finish time of all activities. What is the critical path and what is the length of the critical path? b) If activity I were delayed by ten time units, what would be the impact on the project duration