Question: The network below represents a project being analyzed by the critical path method. Activity durations are A = 5 , B = 2 , C
The network below represents a project being analyzed by the critical path method. Activity durations are A B C D E F G H I and J
Reference: Project
Which of the following statement is false?
A If activity C was delayed by six time units, the project duration will be delayed by one time unit
B The latest start of activity E is
C The slack time at activity H is
D The length of the critical path is
E None of the above, they are all true