Question: The network below represents a project being analyzed by the critical path method. Activity durations are A = 5 , B = 2 , C

The network below represents a project being analyzed by the critical path method. Activity durations are A =5, B =2, C =12, D =3, E =5, F =1, G =7, H =2, I =10, and J =6.
Reference: Project-1
Which of the following statement is false?
A. If activity C was delayed by six time units, the project duration will be delayed by one time unit
B. The latest start of activity E is 17
C. The slack time at activity H is 5
D. The length of the critical path is 30
E. None of the above, they are all true

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!