Question: The normal time for a critical path task is 30 days and the normal cost is $4500. We can crash this task to a maximum

The normal time for a critical path task is 30 days and the normal cost is $4500. We can crash this task to a maximum of 20 days at a total cost of $6500 ($4500 plus $2000 of overtime). What is the slope?

$450 per day

$325 per day

$200 per day

$550 per day