Question: The normal time for a critical path task is 30 days and the normal cost is $4500. We can crash this task to a maximum
The normal time for a critical path task is 30 days and the normal cost is $4500. We can crash this task to a maximum of 20 days at a total cost of $6500 ($4500 plus $2000 of overtime). What is the slope?
$450 per day
$325 per day
$200 per day
$550 per day
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
