Question: The optimistic, most likely and pessimistic time estimates (in terms of days) for a project are given in the table below. What is the probability

The optimistic, most likely and pessimistic time estimates (in terms of days) for a project are given in the table below. What is the probability that the project will be completed before day 67? (You may find P(Z S...) value and leave it like that if you cannot find a Z table) Activity Predecessors Pessimistic time (b) Optimistic time (a) Most likely time (m) 29 47 12 24 16 19 28 16 19 2. 5 14 5 18 DE 2 Attach File Browse Local Files Browse Content Collection Browse Dropbox Windowsu etniesmek icinsel bilgi ayarlarna gidin Question 7 of 10