Question: The optimistic, most likely and pessimistic time estimates (in terms of days) for a project are given in the table below. What is the probability

The optimistic, most likely and pessimistic time

The optimistic, most likely and pessimistic time estimates (in terms of days) for a project are given in the table below. What is the probability that the project will be completed before day 677 [You may find P(Z s...) value and leave it like that if you cannot find a Z table) Activity Predecessore Pessimistic time (b) Optimistic time(a) Most likely time (m) A 17 29 47 B IA 6 12 24 A 16 19 28 ID B 13 16 19 15 14 DE