Question: The optimistic, most likely and pessimistic time estimates (in terms of days) for a project are given in the table below. What is the probability

The optimistic, most likely and pessimistic timeThe optimistic, most likely and pessimistic time

The optimistic, most likely and pessimistic time estimates (in terms of days) for a project are given in the table below. What is the probability that the project will be completed before day 67? (You may find P(Z S...) value and leave it like that if you cannot find a Z table) Activity Predecessors Pessimistic time (b) Optimistic time (a) Most likely time Km) A 17 29 47 16 12 24 IC 16 19 28 D 13 16 19 14 DE 18 The optimistic, most likely and pessimistic time estimates (in terms of days) for a project are given in the table below. What is the probability that the project will be completed before day 67? (You may find P(Z S...) value and leave it like that if you cannot find a Z table) Activity Predecessors Pessimistic time (b) Optimistic time (a) Most likely time Km) A 17 29 47 16 12 24 IC 16 19 28 D 13 16 19 14 DE 18

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!