Question: The PAC function where priorities are set as to what work is to be done on a given day at a work center is dispatching.
The PAC function where priorities are set as to what work is to be done on a given day at a work center is dispatching.
a.
False
b.
True
The make span of an hourly schedule is equal to load of the work center with the greatest number of hours, over the scheduled period.
a.
False
b.
True
A Gantt chart is a basic scheduling tool that is most useful in low-volume systems.
a.
True
b.
False