Question: The partial rough master production schedule for period 6 is given. Is the plan for this period feasible if the planned number of workers for

The partial rough master production schedule for period 6 is given. Is the plan for this period feasible if the planned number of workers for this period is 64 and each worker works 20 days per month and 8 hours per day ?
Rough Master Production Schedule- Month 6
Product Family
Setup Time per Batch (hour)
Average Batch Size
Number of setups
Production Time per Unit (hour)
Total production time (hour)
(setup time + production time)
Production Quantity
A
8
50
5
5.6
1474
256
B
6
150
4
3
1944
640
C
8
100
5
3.8
1986
512
D
10
50
5
4.8
1279
256
E
6
100
5
3.6
1873
512
F
5
75
5
4
1525
375
Total
10,080 hours
Question 1 options:
No, the plan is not feasible because the available time is 160 hours less than the total production time.
Yes, the plan is feasible because the available time is 80 hours more than the total production time.
No, the plan is not feasible because the available time is 80 hours less than the total production time.
Yes, the plan is feasible because the available time is 160 hours more than the total production time.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!