Question: The pathway from project start to conclusion that involves the longest completion time is called the critical path purchasing control level economic order quantity financial

The pathway from project start to conclusion that involves the longest completion time is called the
critical path
purchasing control level
economic order quantity
financial minimum level
 The pathway from project start to conclusion that involves the longest