Question: The pathway from project start to conclusion that involves the longest completion time is called the _ _ _ _ _ _ _ _ _
The pathway from project start to conclusion that involves the longest completion time is called the
Group of answer choices
critical path
economic order quantity
purchasing control level
financial minimum level