Question: The pathway from project start to conclusion that involves the longest completion time is called the _ _ _ _ _ _ _ _ _

The pathway from project start to conclusion that involves the longest completion time is called the __________.
Group of answer choices
critical path
economic order quantity
purchasing control level
financial minimum level