Question: The process time for each station is as follows: Make Dough =90 minbatch, Mx Filling =7 minbatch, Roll 8 Cut =26 mirvbatch, Buko =20 minbatch,
The process time for each station is as follows: Make Dough =90 minbatch, Mx Filling =7 minbatch, Roll 8 Cut =26 mirvbatch, Buko =20 minbatch, and Pack =16 minrbatch. a) What is the bottleneck of this bakery? A. Make Dough B. Mox Filling C. Roll \& Cut D. Bako E. Pack b) The botteneck time of the bakary is minbatch (round your response to the nearest integer). c) The throughput time of the bakery is minbatch (round your response to the nearest intogev) d) Assuming they work 40 hours per week, the overall weekly capaoty of this bakery in batches of croissants (round your response to bne noarest integed) e) Assuminq they work 40 hours ber woek, if the bakorv adds 1 more dough-makine staton(s), the overall weeklv capacitv would be botches of croissants (round vour resoonse fo the