Question: The program was planned years ago, before there was a massive introduction of new technology. While planning the next project in this program, the project

The program was planned years ago, before there was a massive introduction of new technology. While planning the next project in this program, the project manager has expanded the scope management plan because as a project becomes more complex, the level of uncertainty in the scope: A. Remains the same B. Decreases C. Decreases then increases D. Increases