Question: The project duration in a network can be determined by the largest value of which variable associated with the critical path? A . Earliest start

The project duration in a network can be determined by the largest value of which variable associated with the critical path?
A. Earliest start time
B. Earliest finish time
C. Slack time
D. Activity time
 The project duration in a network can be determined by the