Question: 1 . Consider the following network diagram for a project ( the times shown are in weeks ) : ( a ) Do a forward
Consider the following network diagram for a project the times shown are in weeks:
a Do a forwardbackwards pass calculation and provide all four times earliest start time, earliest finish time, latest start time, and latest finish time Identify the slack for each activity and identify the critical path. points
b How long will it take to complete this project? points
c Can activity D be delayed without delaying the entire project? If so how many weeks? point
d Can activity C be delayed without delaying the entire project? If so how many weeks? point
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
