Question: The project has reported a variance but the PM reports that this was due to a one-time problem. She expects the remainder of the project
- The project has reported a variance but the PM reports that this was due to a one-time problem. She expects the remainder of the project will continue as originally budgeted. AC=$72,000, EV=$67,000, BAC=$175,000. Which method should be used to calculate EAC and what is the new EAC? (2 points)
Please show step by step.