Question: The project manager has just determined that three functional managers with a high interest in the project hold a particularly high degree of influence in

The project manager has just determined that three functional managers with a high interest in the project hold a particularly high degree of influence in the allocation of enterprise resources. In what activity is the project manager involved?
Developing the stakeholder engagement plan
Identifying stakeholders
Determining team assignments
Developing the resource plan