Question: The project manager has just determined that three functional managers with a high interest in the project hold a particularly high degree of influence in
The project manager has just determined that three functional managers with a high interest in the project hold a particularly high degree of influence in the allocation of enterprise resources. Where is the project manager likely to document this information?
A. Stakeholder analysis B. Resource management plan C. Stakeholder engagement plan D. Stakeholder register